When works involve structural changes, new bathrooms, or extensions, additional approval from Dubai Development Authority (DDA) or Dubai Municipality (DM) is required.
These approvals confirm compliance with load-bearing, plumbing, and safety regulations.
We coordinate this process through licensed structural consultants, but all submissions, communication, and follow-up are handled by The Big Fitout on your behalf.
Typical documentation includes:
- 
Structural drawings and load calculations.
 
- 
Consultant approval stamps.
 
- 
Villa layout and elevation drawings.
 
- 
DDA/DM inspection reports (if required).
 
Preparation usually takes 2–3 weeks, and approval time varies depending on the complexity of the scope but on average the approvals are received in 4-6 weeks from application.